Xypex Admix is blended into the concrete mix at the time of batching to waterproof and protect concrete from the start. It outperforms other methods because of its unique ability to become a truly integral part of the concrete matrix. The Admix C-Series has been specially formulated to meet varying project and temperature conditions. Xypex Admix C-500 meets concrete practices that incorporate additives such as fly ash and slag. Xypex Admix C-1000 is designed for typical Portland cement-rich concrete. Xypex Admix C-2000 is designed for projects where extended retardation is required. For ease of use, Xypex Admix is available in pails, bags or soluble bags. Click below for more details.


XYPEX Concrete Waterproofing Admixturess

Installing Additive

Xypex Admix is added to the concrete at the time of batching. The sequence of procedures for addition will vary according to the type of batch plant operation and equipment.

1. READY MIX PLANT - DRY BATCH OPERATION

Add Xypex Admix in powder form to the drum of the ready-mix truck. Drive the truck under the batch plant and add 60% - 70% of the required water along with 300 lb. - 500 lb. (136 kg - 227 kg) of aggregate. Mix the materials for 2 - 3 minutes to ensure the Admix is distributed evenly throughout the mix water. Add the balance of materials to the ready-mix truck in accordance with standard batch practices.

2. READY MIX PLANT - CENTRAL MIX OPERATION

Mix Xypex Admix with water to form a very thin slurry (e.g. 15 lb. - 20 lb. of powder mixed with 3 gallons of water). Pour the required amount of material into the drum of the ready-mix truck. The aggregate, cement and water should be batched and mixed in the plant in accordance with standard practices (taking into account the quantity of water that has already been placed in the ready-mix truck). Pour the concrete into the truck and mix for at least 5 minutes to ensure even distribution of the Xypex Admix throughout the concrete.

3. PRECAST BATCH PLANT - PAN TYPE MIXER

Add Xypex Admix to the rock and sand, then mix thoroughly for 2 - 3 minutes before adding the cement and water. The total concrete mass should be blended using standard practices.

Note:It is important to obtain a homogeneous mixture of Xypex Admix with the concrete. Therefore, do not add dry Admix powder directly to wet concrete as this may cause clumping and thorough dispersion will not occur. For further information regarding the proper use of Xypex Admix for a specific project, consult with a Xypex technical representative.

Xypex Chemical Corporation
13731 Mayfield Place
Richmond, BC V6V 2G9
Tel: (604) 273-5265
Fax: (604) 270-0451
Tollfree: (800) 961-4477
E-mail: info@xypex.com
Web site: http://www.xypex.com





 |   |   |